Today, Chapman Metering began installing smart meters for the remaining accounts served by the Lindahl (#62) substation (see map below). They expect it will take 2-3 weeks to complete meter installations in the Lindahl area, and then they will move onto the Shellsburg (#55) substation area. Reminder postcards were sent out to the affected members living in these areas late last week.
Chapman will change out approximately 1,100 meters (including Heat Plus accounts) during this phase of installation. They expect to complete the meter installations in the Shellsburg area in April.
Smart meter installation is the next step in maximizing the capability of the technology ECI REC has been putting in place over the past decade. The ECI REC team is here to address any questions you may have about the new meters. Please feel free to call or email us for more information.